PLANEJAMENTO DE PARADA DE MANUTENÇÃO EM OBRAS DE CONSTRUÇÃO E MONTAGEM EM REDES DE DISTRIBUIÇÃO DE GÁS NATURAL VEICULAR (GNV): SIMULAÇÃO DE RECURSOS NO MSPROJECT

PARADE PLANNING MAINTENANCE WORKS IN CONSTRUCTION AND ASSEMBLY IN DISTRIBUTION NETWORKS OF NATURAL GAS VEHICLE (NGV): SIMULATION OF RESOURCES IN MSPROJECT

Authorship

DOI

10.5151/2594-5327-23046

Downloads

685 Downloads

Abstract

Segundo o senso de 2010, o Brasil é o sexto maior país do mundo em extensão territorial. Com base nessa informação, se faz necessária a existência de um meio eficaz para o deslocamento de produtos como petróleo e gás natural, sendo utilizadas tubulações como um meio logístico. Para que estas possam realizar o deslocamento dinâmico, deve haver uma prática de manutenção aprimorada visando evitar falhas de menor intensidade até acidentes como vazamentos, explosões, etc.. Para a execução da atividade de manutenção é indispensável investigar as condições existentes no trecho, portanto é necessário realizar ensaios não destrutivos como Líquido Penetrante, Ultrassom, Medição de Espessura, entre outros. Em caso de falha, se utiliza técnicas de reparação, como a soldagem MIG pulsado. Durante o esmiuçar deste trabalho, parâmetros relacionados à gestão de projetos ao dimensionamento de mão de obra aplicada na parada de manutenção no trecho aéreo. Conhecendo a extensão do exemplo utilizado, 600 metros da estrutura tubular, o qual deve ser submetido às intervenções e admitindo que os mesmos sejam bastante onerosas, é preciso que haja um planejamento adequado na realização das funções e seus profissionais associados, assim, reduzindo o tempo de execução da manutenção, com o intuito de minimizar custos. Portanto, foi utilizado para o planejamento e organização o software Microsoft Project, que auxilia no processo de decisão, facilitando o controle de tempo e dinamizando a execução da parada.

 

According to the sense of 2010, Brazil is the sixth largest country in area. Based on this information, it is necessary that there is an effective means for moving products such as oil and natural gas, pipelines being used as a means logistics. So that they can realize the dynamic displacement, there must be an improved maintenance practice in order to prevent failures of lesser intensity to accidents such as spills, explosions, etc. For the execution of the maintenance activity is essential to investigate the conditions existing in the stretch, so you need to perform NDT as Penetrant, Ultrasound, Thickness Measurement, among others. In case of failure, using repair techniques such as pulsed MIG welding. During scrutinize this work, parameters related to project management for the design of labor applied to the maintenance shutdown in air passage. Knowing the extent of 600 meters from the tubular structure which must be subjected to interventions and admitting that they are quite costly, there must be proper planning in carrying out their functions and associated professionals, thus reducing the runtime maintenance, in order to minimize costs. Therefore, it was used for the planning and organization software Microsoft Project, which assists in decision-making, facilitating control of time and streamlining the execution of arrest.

Keywords

Planejamento; Parada de manutenção; Nivelamento de recursos; Mão-deobra.

Planning; Stop maintenance; Resource leveling; Manpower.